Friday, May 2, 2008
A Public Thank You
So, yesterday, I had an interview to prepare for and the Missus managed to get a bathroom wall framed in on her own before I joined her--some pretty heavy work to do on your own. Anyway, we were at the site until nearly 8:00, and by the time we finished up our paying work it was after 9:00. Even as late as it was and as tired as she had to have been, my wife made us fresh fettuccine to go with a quick Bolognese I had whipped up. It made the meal and was a wonderful comfort after a hard day.
I consider myself a lucky man. A VERY lucky man.
Having a partner like her makes this project much more pleasant.
Now, back to your regularly scheduled DIY blog postings.
Tuesday, April 29, 2008
Rehabbing an Old House Step 3: Estimating
This installment follows Step 2: Selecting
http://www.rehabordie.com/2008/02/rehabbing-old-house-step-2-selecting.html
and Rehabbing Manual Step 1
So, you've found a place that you like and that's in decent shape. Time to make an offer, right? Not so fast! You've got more work to do.
You can't make a responsible offer until you know how much money it's going to cost you to make it livable or the way you want it. Also, if you're getting a rehab loan, you're going to have to have good estimates for the bank too, even for things you intend to do yourself.
There's more to it than you'd think. You don't want to under-estimate, either, as you'll end up with a place that you're paying a mortgage on but that hasn't been painted or carpeted or which ends up looking crummy because you had to cheap-out on your finish.
First off, you're going to have some demo expense. If it's a major gut job, don't do this yourself. It's hard, it's nasty, and it's dangerous, and you don't save all that much money. Typically, demolition will run $1.50-$2.50 per sq. ft. You may have to add in dumpster expense ($250-$700) and any materials.
You're also going to have some soft costs like permits, closing costs, and architect (though if you aren't changing things much, you may not need a pro).
You'll need to secure the building from the elements and from miscreants. That means get several roof estimates, as well as estimates for windows and doors. New windows should be ordered a bit later in the process if you want to avoid potential damage, but it's nice to have a warm, safe place. Windows can be expensive, though if you have more time than money, repairing them is not a huge deal. There are many books on this. Doors are easy to find on Craigs list, and don't forget any basement access door that might need to be replaced.
If the electrical system is old knob and tube you're going to want to replace it. It's dangerous. Get several estimates from credible electricians. You can probably do a good bit of wiring yourself but you're going to want to bring in a pro to hook things up to the breaker box and to consult with you. Do your homework and remember that electricity is dangerous.
If the plumbing is iffy (and you'll want to have a plumber check it out if you don't intend to replace it), you can do much of the PVC work yourself, but a good plumber can move mighty quickly. Also, you pay a plumber for what he knows more than what he does.
If the HVAC system is old, you'll probably want to replace this, too. Get a couple estimates. You can find cheap furnaces sometimes, but most of the time, your HVAC guy can get this stuff more cheaply than you can.
Study the foundation from the outside and look for any potential drainage issues. You'll want to address those quickly and some might require a pro so don't forget to estimate for that, if necessary.
What about insulation? You'll probably want to add insulation. Much you can do yourself but not all. Will you be using spray foam? Some you can do yourself, but others require professional help.
If you're going to have the walls opened up, you might want to consider a central vac system. They aren't too expensive, and you can do it yourself, but they still need to be budgeted for.
You'll want to visualize the place as if it were done and list things you'll need to price out. Drywall and all that goes with it (mud, tape, screws, etc.). Trim (doors, windows, baseboards). Window treatments. Primer and Paint (remember, don't skimp on the paint--labor is the expensive part--you don't want to paint any sooner than you have to). Stains. Electrical fixtures.
Will you be sanding the floors or covering them over? Get a bid on sanding, unless you've had experience or have an option to practice somewhere. Don't forget carpet or any laminate flooring too.
Don't forget appliances. You may need new washer and dryer, oven, stove, fridge, range hood, and the like. Maybe you already have these, but if not, you'll need to add this into your estimate.
Cabinetry for bathrooms and kitchen? That can get expensive, but it can also be done reasonably affordably. Don't forget drawer pulls and handles too. Ikea has some great planning tools, if you want a starting place. Just don't forget to get estimates.
You're going to want to spend some time and money on landscaping too, in all likelihood. If it's more than a few pansies, you'll want to include a budget for that too. While you're outside, make sure that you don't need to paint.
You'll need some tools, too. A rehab should NOT be an excuse to go on a buying spree at Home Depot. Some tools you'll need and you should buy them new. Other tools you may not need, or you may not need to use much. Those are tools that you might want to borrow or rent. Other tools you might want to snag off Ebay, Craig's List, and even pawn shops. Don't forget yard sales. You can blow $2000 in a heart beat buying new tools and you don't have to. Plan early, be creative, and accumulate the tools that you'll need. There are books on this, including the one recommended in Step 1, so we won't belabor the issue, but rather offer the things we KNOW you'll want to have.
(Pretty Much) Imperative tool list:
Circular Saw
Cordless Drill
Bits: Spade, Masonry, etc.
3' Level
Framing Square
Pull Saw
Wood Chisels
Wide, 25' Tape Measure
Utility Knives
Work Gloves
Hammer
3' Sledge
Pry Bar(s)
Safety Glasses
Steel Toe Work Boots
N100 or P100 Respirator
Miter Box/Saw
Don't gloss over all the nails and screws and fasteners and glue that you may need. This, too, adds up.
Once you've got your budget, you're going to want to add 10%-15% contingency. Plan on discovering things that you have to do or things that you'll really want to do. Plan on time delays. You may want to have two sets of estimates, one for the bank and one for your own use, especially if you're going to be doing a lot of work yourself or bartering with tradespeople. In any case, once you have your estimates, then it's time to make your final determination and make an offer. Even then, you may want to arrange financing first.
Tuesday, April 22, 2008
Had to move the wall.
We met with our HVAC guru, (www.PeakHVAC.com) and we'd been trying to figure out the best way to heat and cool the house. We at first thought we'd head a vent and return on each side of the dining room fireplace, but it turns out we'd need a lot more space for a second vent to carry air to the 3rd floor and it would make the dining room all.... wonky. Also, it would mean branching out in the basement and taking half of the vent-age (my word, not Chuck Phaeler's from Peak HVAC, heh heh) to the north side of the house and half to the rear, and we'd be talking uber-soffets like an encompassing, but warm, octopus.
So we determined we could fit the HVAC main ductwork up from the basement, up through the northeast corner of the kitchen (practically unused space), into the northeast corner of the bath/laundry room, and then into the 3rd floor. This way, the ductwork stays in a central location, and only branches out from the 'trunk' at the level it is needed.
There was one problem though with the return that was planned for the kitchen wetwall.
Yeah.
Well, we planned the location of the kitchen wetwall ever so carefully, making sure that the wetwalls on the second and third floor would all like up and even distribute some weight. I'm, not kidding, we spent HOURS trying to determine the exact location for premium placement and ease of use. But did we go into the basement and check out the ceiling to make sure that the joists that ran throughout the house also matched up in the basement? Nooooo, that would have been way too smart. Way.
Yeah.
So we built the kitchen wetwall not only right on top of a joist, but to make it all the more painful, it was a double joist.
The plumbing that we so carefully planned for had to come up through the wetwall on the west, then back across over the kitchen to the east, then back up through the floor to meet the bathroom on the second floor. OK, plumbing disaster averted... but the HVAC? Not so easy.
A few days after we made the plumbing work-around, Chuck (the HVAC boss) made the call that we'd have to either move the wall, or we'd have to have an angled return in the dining room that stuck out about 3" on the floor and sloped back to the wall to get around the joist screw up.
We moved the wall.
Now I'm halfway tempted to tell the plumbers that we can now run the PVC up the wetwall the way it was supposed to go in the first place-- just to see the looks on their faces.
Today's agenda: Replace last two rotted floor joists on the first floor with 2x12" PTL (Pressure treated lumber), and start pulling up the rest of the old tongue and groove 1" flooring (wearing a mask this time so as not to kill myself by inhaling the mold on the underside THIS time.) Then overlay with two full sheets of 1/2" OSB ( laid out so as to overlap and not have the edges on the second layer line up with the edge of the sheets underneath, aka staggered layout) and finish sistering 2x6's to the rotted joists on the 2nd floor for floor supports, fix the holes with OSB, then laying single sheets of OSB for the final subfloor prep.
Unless I have to move another wall.
Thursday, April 10, 2008
Copy Cat?
Here's one great resource Covington Properties.
Of course, just driving around Covington can give you some options too.
There may be financing incentives and low interest loans for owner-occupied properties. I suspect that prices are negotiable in the current environment, too. In fact, I'm confident that many properties can be purchased for less than one could build them.
If you need a contact person, just ask.
Oh, and note well, many of the properties are in better shape than ours was.
If you're looking for step-by step guidance, you might want to start with our Rehab Manual entries.
Tuesday, April 8, 2008
Fixed the downspout.
We had to have the whole thing cut out.
I'd call that a poor choice in strainers considering the amount of water the boxgutter is designed to move, but at least now (crossing fingers) we can keep the rain off of the house, not in the second floor, not in the basement and away from the house and into the storm drains.
I hope.
We'll see. It's supposed to rain for the next three days.
Friday, April 4, 2008
Box gutter or wading pool? -- You Decide.

This is the view from our third floor facing North. You can Cincinnati in the background through the wispy clouds and rain. It's a great view at night when the visibility is better.
By the way, the house at the end of the alley behind us with the red tin roof has been for sale for a while now. It's a great looking place but as far as I'm concerned, needs new electric (still has knob and tube setup.) I think they're asking $189K.
If you're interested, you may want to check it out.
Anyway, what you CAN see a lot clearer from this vantage point is our brand new boxgutter, the one that was leaking for so long that we had to have the 'water feature' underneath because it was pouring water into the house when Benchmark Roofing came and started the box gutter, but didn't get back to finish it for a few weeks.
Here it is in all of its glory, still unpainted, and hey-- wait--- Isn't a box gutter supposed to move the water into the downspout and out to the storm drain?
Sure, that's what they're SUPPOSED to do, but what the heck is happening here?
Oh, yeah, it's flooding and pouring over the side.
Again, while working on the wetwall for the upstairs bath/laundry room, we thought we MUST be hearing the next door neighbor's gutter. It couldn't possibly be the gutter or the downspout. No way.Way.
My guess is that something the roofers left on the roof... a glove, a bottle, a cup, SOMETHING is clogging the downspout. There is no water going through it, just over the side. We just spent a bundle unclogging and replacing the cast iron pipe at the foot of the downspout, so we know it's not that, and it's not like there are any leaves on the trees...
Damn damn damn. When we will ever get (and keep) the water out of the house??? I'm wet, I'm dusty, and I need a shower. And I'm very disappointed right now.
Tuesday, April 1, 2008
Wetwalls going up
First, as mentioned before, we blocked in the walls and the ceiling joists in between the furring strips and the ceiling joists where the wet wall was to be located. (We're planning on having the wet wall continue above onto the second floor for the second floor bath as well, to make things easier.)These blocking areas are to help support the freestanding wall that we are putting in. The blocking will act as nailers and the sucker shouldn't move a millimeter once it's up.
I measured the length of the wall from our floorplans, double checking that we'll have enough room for the kitchen counter tops, double sink, dishwasher, etc... then cut the 2 lengths of 2x6's for the top and the bottom.
I measured each distance from the ceiling joist to the floor, then subtracted 3" for the boards at the top and the bottom of the frame, then I subtracted another quarter of an inch for maneuverability when raising the wall from horizontal to vertical. (You will need that extra 1/4" for room to set it up, otherwise, it won't fit.)
Since the length of the wall was not a multiple of 16" but we needed to have the 16"OC measurements for the drywallers, we just started the measurements from the open end of the wall (the right side in these pictures) and measured in 16" towards the attached wall, then marked both the header board and the footer. Then I lined up each board on the floor and nailed it into place at the top and bottom, according to the 16" mark.
There's an extra 7" space away from the attaching wall where we had leftover space from the last 16" measurement. No problem.
Then we raised the wall up, maneuvered it into placed with a little jostling and kicking, then secured it to a ceiling joist with a single screw.
We're already building the framing wall in the kitchen, but I don't have any pictures yet. Maybe it has something to do with that bottle of wine in the last picture... heh heh. Okay, so we toasted our first built wall. It was a long day.
Thursday, March 27, 2008
Warning: Head-Bone Connected to the Pain-in-the-Neck-Bone
BUT, it is a fact of rehabbing life that when you fix something, you find the next weakest link in the chain of jerry-rigged repairs and jake-legged improvements, plus any naturally occurring problems. When a box gutter is dumping water out the wrong end, for instance, it doesn't send water down the downspout and into the drain out to the storm sewer. When you fix the box gutter, re-attach the downspout and then get a couple inches of heavy rain, you send hundreds of gallons of H20 down that drain. That drain that hadn't seen water in years. That drain that was badly clogged.
So, water was not running down the drain. I was unaware of that. For a while. Then, I heard water running. In the basement. Uh-oh...
It seems that some time ago, a prior owner attached a kitchen drain to the storm drain, just below the downspout, and not very well at that. Since there were hundreds of gallons of water coursing down with no way to get through the drain, the water found the next weakest link and that was around that former kitchen drain hookup, in the basement.
Fortunately, or unfortunately, the water was coming in at the dirt end of the basement, actually in the crawl space, which we have currently exposed. It drained right into soil, so there was no real damage, but there's a funky smell and a bit of moisture lingering at the north end of the house.
The good news is our plumber, Bert. I called him, he came. He said he'd have to cut the concrete to get at the drain and that it would take a couple days to get to it. It took him one and they were done early in the morning. I had intended to take a few pictures, but they were in and out before I could move. They under-promised and over delivered. Me like. I'll be talking more about our plumber later.
One bit of upside is that they hooked up a "Y" connector so that I can drain water off the concrete patio and into the drain instead of down the walk or up against our house.
It could have been worse, so I'm thanking our lucky stars.
Now, back to furring and framing.
Friday, March 14, 2008
False Alarm... back to blogging.
And now, to the roofing.
Well, they're not done yet.
And it's raining.
I got to give it to the laborers, they knew they weren't done and so they rigged up a clever temporary fix until they get back, which is right where the top boxgutter from the gable roof meets the valley at the shed roof. As you can see, they've taken a bit of the metal and laid it over the top of the junction so that the water drains down to the shed roof into the lower box gutter. I just hope we don't have any wind...
Here's the boys hard at work on a beautiful 55 degree day- the first dry one in a few weeks.[By the way the house directly to the right of ours is for sale by the city. Owner-occupied rehabbers come take a look! Heck, make an offer on the one to the left of us, too. Currently it's being rented out as three different apartments and is in desperate need of a single family owner.]
Back to the roof: the flashing. I would've asked the laborers if they were planning on a little more work on the flashing, but my Spanish isn't so good anymore.
This is the East side of the house, looking up at the roof. Maybe it's just me, but I'm not so happy with the way this looks. I have to assume they're just not finished on that part, either. I would have thought that the underside would have gone down first, but I'm not a roofer.The West side also needs some finishing work, too. The flashing so far is buckling up towards the back, and the picture at the bottom of this post shows some mighty big gaps from the inside of the 3rd floor.
I was tempted to take down the plastic we have hung up through the second floor, the 'water feature' as the hubby calls it, but he said no- wait until they're finished, so up it stays.
I can't wait to have a finished roof. Everything we've been putting off depends on it.

Furring & Roofing : a busy day.
First of all, I wanted to show another image of what we did with the furring on the second floor with the 2 foot oc measurements and how we furred in the windows. The blue lines represent where we had to add in the extra 2x4's, and the orange lines represent the regularly spaced 2' 2x4's.Of note is the gap we've left at the bottom near the floor. We've spaced for another 2x4 along the bottom and a 1 1/2" gap for wiring and electric. This space is so that we can cover the wires at the vertical 2x4's with a 1 5/8" standard nailer plate (to prevent the drywallers from hitting a nail through the wiring at the bottom of the wall.)
Also, the red arrows point to where the E-W wall used to attach to the East wall. Here, of course, is exactly where a 2x4 needs to go, so we pulled out the rest of the plaster (most of it was pulling away from the brick from the demo process anyway) and we're tapconning and gluing in small 1"x2" boards to the brick, as to be flush with the plaster for when the 2x4 goes on top, it will be flush with the other 2x4's.
It should work.
OK, I was going to write about the roofing process... it's day 3 for Benchmark Roofing and I've got a few problems, but Reimier Lumber just called with our lumber delivery order, So we've got to run.
To be continued....
Tuesday, March 11, 2008
Concealed Shoes - an alternative to human sacrifice.
The demo team turned them up during the demolition process, so I'm not sure exactly where in the house they were found, (we're trying to find the crew to ask them) but I'm ever so grateful they were set aside for us. What am I referring to? Old (single) shoes hidden in the walls during the original construction of the house, around 1860.
I thought it was odd, but nevertheless, very very cool. There were six shoes altogether. Two adult shoes (that didn't match each other) and four children's shoes, all mismatched as well. The adult shoes barely held together and I'm sorry to say, didn't get saved. I really regret not keeping them now, even if they were barely soles and cloth and a couple of grommets. Now that I know a little more about the whys and wherefores, I'm kicking myself with those two lost shoes.
So here's a little bit of what we picked up in our research of concealed shoes from the Wayland Historical Society in Massachusetts:
When owners of old houses begin renovations, they should be aware that they might turn up some unexpected treasures in the walls of their homes. Two Wayland families have discovered a trove of old shoes hidden in the house walls, a reflection of an ancient superstition that hiding shoes in a house as it was being built, would ward off evil.
Jennifer Swope, assistant curator of the Society for Preservation of New England Antiquities, points out that although hundreds of these concealed shoes have been found in buildings in both Europe and Eastern United States no one has ever photographed these finds in the exact site where they have been found.
When tearing out the wall in an old chaise house about eighteen years ago, James and Mary Reed found a baby's white, ankle-high shoe, some small wooden toys and some ears of corn. Their Old Sudbury Road home has been the site of so many additions since the earliest part was built about 1750 that they were not sure whether the shoes were hidden at the time the chaise house was built or in a later renovation.
The Raymond Johnsons who live in the Brintnall-Loker house, the oldest house still standing in the Cochituate area, have found shoes in two different locations in their home. In an
upstairs wall, near a window, four well-worn shoes--none of them mates--were found. The photograph at the right shows a common custom of having several members of the family each contribute one shoe to the cache. In the second instance, a toddler's little shoes had been deliberately built into the wall near a downstairs fireplace. Hidden with it was an old sleigh bell. The toy tree shown right was found with shoes in the Reed house. The Johnson shoes are currently being researched to determine their age and whether they have been buried in the walls at the time the house was built in 1740, or whether they were added in a later building improvement.
The Wayland shoe finds have been listed on an international index of concealment shoes, maintained at the Northampton (England) Museum. More than a thousand concealment shoes, some dating back to the fourteenth century, have been reported in Western Europe. In this country these shoes have been discovered mostly in New England, but there have also been reports of buried shoes as far south as Virginia and far west as Missouri.
Why would shoes be deliberately built into a home or public building? Some have speculated that the tradition stems from the prehistoric custom of killing a person and placing the body in the foundation to insure that the building holds together. Later shoes were used as a substitute for a human sacrifice. Shoes may have been chosen, because over time they take on and keep the shape of the wearer's foot. Shoes were hidden near openings in the home--doors, windows, chimneys--the perceived weak places in the building that were thus protected from evil by the shoe owner's spirit.
About half the shoes registered in the concealment index are children's shoes. Women's shoes are more common than men's. Shoes are almost invariably well worn, perhaps because the donor didn't want to waste an expensive new shoe on the project, or perhaps because a well-worn shoe is more likely to retain the shape of the wearer's foot and hence his spirit. Though shoes are the common denominator, more than two hundred different personal possessions--coins, spoons, pots, goblets, food, knives, toys, gloves, pipes, even chicken and cat bones--have been found hidden with them.
Considering how widespread and long lasting this folk belief has been, it is curious that nowhere was it described in writing until references began to appear in mid-twentieth century archaeology literature in scholarly journals. Some speculate the tradition of hiding shoes was a male superstition, kept secret almost out of fear that telling about it would reduce its effectiveness. Others feel contemporary writers did not describe it since superstition ran counter to prevailing religious beliefs and the Puritans punishment of witchcraft and magic was well-known.
When removing walls especially around windows and doors, under roof rafters and behind old chimneys, homeowners should be aware of the possibility of turning up concealment shoes. While most are found in eighteenth and nineteenth century homes, a find hidden as late as 1935 has been reported. If shoes are found, they should left exactly as they were discovered and photographed. Items found with the shoes are as important as the shoes themselves and should also be saved.
Sources include: Displayed Shoes and Concealed Ones, Early American Homes, April 1999; Hidden Shoes and Concealed Beliefs, Archaeological Leather Group Newsletter ; Shoes Concealed in Buildings, NorthamptonMuseums Journal 6, December 1969 ; Ralph Merrifield, The Archaeology of Ritual and Magic , B.T. Batsford Ltd., London, 1987
So here's our treasure:Sunday, March 9, 2008
Why you use 2' increments for furring.
When furring in the windows, we almost made the huge mistake of mis-attaching the furring strips.
For the sake of example, let's say we started in the right hand corner of a room and were laying furring along the wall to the left. Since we'd never done this before, we started with the assumption that when you started from the corner with the first furring strip, you'd measure from the exposed edge (the left side of the 2x4 ) of the corner 2x4, measure over 24" to the left, then lay the second furring strip to the right side of that 24" mark. So far so good.
The question was what happens when you come to a window, or a door frame. What then? I thought, well, you just frame in the window on all four sides, then continue measuring 24" to the left of the left side of the window and start measuring 24" from there. WRONG.
Apparently, you need to keep the 24" pacing around the wall and room, regardless of what gets in the way, because of the drywall 4'x8'measurements. So, if you need to add more strips around a window or a door frame that is not at a pre-measured interval, you just add in new furring where you need it.
In the animated image here, I've shown what we did, and why. CLICK THE IMAGE.Note (in the animation) the orange arrows show where we added in the additional furring to the left, above and below the window to accommodate the window, but did NOT adjust the 2' spacing of the regular furring strips, and how the drywall would be laid in (from the ceiling downwards) after everything was in place.
Again, I note: In the 'preview' image, it doesn't show the animation, so you'll need to click on the image to see the full presentation.